Which of the Following Describes the Activities Appropriately Performed by the Project

Question 22

Multiple Choice

Which of the following describes the activities appropriately performed by the project team during Perform Qualitative Risk Analysis?​ 


A)  Team members assess the probability of occurrence and severity of impact for identified risks. 
B)  Team members develop contingency plans for all risks to avoid adverse impacts to project objectives. 
C)  Team members identify potential risk events. 
D)  Team members define how to conduct risk management activities for the project.

Correct Answer: