Multiple Choice
Which of the following describes the activities appropriately performed by the project team during Perform Qualitative Risk Analysis?
A) Team members assess the probability of occurrence and severity of impact for identified risks.
B) Team members develop contingency plans for all risks to avoid adverse impacts to project objectives.
C) Team members identify potential risk events.
D) Team members define how to conduct risk management activities for the project.
Correct Answer:

Verified
Correct Answer:
Verified
Q17: All of the following activities are appropriate
Q18: All of the following describe the appropriate
Q19: A risk management plan should define who
Q20: Which of the following quantitative risk analysis
Q21: A _ presents a hierarchical organization of
Q23: All of the following describe an appropriate
Q24: Which of the following activities illustrates a
Q25: The process of defining how to conduct
Q26: Which of the following activities illustrates a
Q27: When complete,the risk register presents the results