All of the Following Activities Are Appropriate Upon Completion of Risk

Question 17

Multiple Choice

All of the following activities are appropriate upon completion of risk response planning EXCEPT: 


A)  The risk register should be updated to reflect the risk response strategies. 
B)  The risk register should be baselined after planning is completed, and should not be updated once the project is in flight. 
C)  The project plan should be updated to reflect any changes to the project schedule, budget or resource assignments. 
D)  A single person should be assigned as the owner of each risk.