Which of the Following Activities Are Typically Included in a Project

Question 22

Multiple Choice

Which of the following activities are typically included in a project kick-off meeting?​ 


A)  The project manager evaluates team member performance. 
B)  The project team collects lessons learned for use on future projects. 
C)  The project manager outlines the project goals. 
D)  The project sponsor brings in a facilitator to conduct a brainstorming exercise