Which of the following serves as a pre-condition that must be met in order for a project kick-off meeting to be successful?​ 


A)  An atmosphere of trust and relationship building should be set by all. 
B)  Project performance results should be calculated and made available to team members. 
C)  Compensation packages and benefits plans should be shared with all team members. 
D)  The meeting location should always be off-site