Multiple Choice
Which of the following is not a common difficulty in the design of project reports?
A) Providing too much detail
B) Having too many interface modules
C) Poor correspondence to the parent firm's reporting system
D) Poor correspondence between the planning and monitoring systems
Correct Answer:

Verified
Correct Answer:
Verified