Short Answer
There are several conventions used to aid in estimating percent completion.Match each rule with its description.
A)50-50 rule
B)0-100 percent rule
C)Critical input use
D)Proportionality
1)This commonly used rule is also based on percentages,but uses time (or cost)as the critical input.
2)This rule assigns task progress according to the amount of an important input that has been used.
3)This rule allows no credit for work until the task is complete.
4)Fifty percent completion is assumed when the task is begun,and the remaining 50 percent when the work is complete.
Correct Answer:

Verified
Correct Answer:
Verified
Q1: _ is collecting,recording,and reporting information concerning any
Q2: In earned value Analysis,EAC refers to the
Q4: If CSI is less than 1,it is
Q5: List and describe five telltale signs of
Q6: In earned value analysis,(CPI)(SPI)= _.<br>A)CV<br>B)TPI<br>C)CSI<br>D)SV
Q7: The project control process should be viewed
Q8: In earned value Analysis,BAC refers to the
Q9: For project management,there are three distinct types
Q10: There are several conventions used to aid
Q11: In earned value Analysis,the 0 - 100