Multiple Choice
There are several conventions used to aid in estimating percentage completion.Which of the following is the most popular?
A) 50-50 rule
B) 0-100 percent rule
C) Critical input use
D) Proportionality
Correct Answer:

Verified
Correct Answer:
Verified