Multiple Choice
In earned value Analysis,the 0 - 100 percent rule allows __________.
A) 100 percent credit before starting work and 0 percent credit after the completion
B) 0 percent credit when work begins and 100 percent credit when the project is complete
C) 0 percent credit when work begins and 100 percent credit at completion of the activity
D) 0 percent credit at completion of the activity and 100 percent credit at formal acceptance during scope verification
Correct Answer:

Verified
Correct Answer:
Verified
Q6: In earned value analysis,(CPI)(SPI)= _.<br>A)CV<br>B)TPI<br>C)CSI<br>D)SV
Q7: The project control process should be viewed
Q8: In earned value Analysis,BAC refers to the
Q9: For project management,there are three distinct types
Q10: There are several conventions used to aid
Q12: What is the relationship between management level
Q13: There are several conventions used to aid
Q14: In earned value analysis,the _ is computed
Q15: Alderton suggests telltale signs of project trouble.Match
Q16: List the four conventions used to aid