Multiple Choice
What does "EVM" stand for?
A) Extra Value Materials-premium quality raw materials at the project site.
B) Enterprise Vacation Matrix-A chart indicating team members planned vacation absences
C) Earned Value Management-a technique for measuring project progress objectively.
D) Early Vision Management-An technique used in early project planning meetings for activities that set expectations to highlight and avoid "scope creep."
E) External Variance Measurement-identifying the degree to which project time and cost variances were due to forces and issues uncontrollable by the project manager.
Correct Answer:

Verified
Correct Answer:
Verified
Q14: PERT is an abbreviation for which of
Q26: An event unit package is a subdivision
Q44: A project may be defined as a
Q51: You have collected the data for a
Q54: Below are the data for a Time-Cost
Q58: You have collected the data for a
Q63: One of the advantages of a functional
Q65: A project starts out as which of
Q85: Earned value management (EVM) is a technique
Q90: The critical path of activities in a