Multiple Choice
A project manager is using a simple scoring model to decide which of four projects is best,given the company's limited resources.The criteria,importance weights,and scores for each are shown in the table.Which project should be chosen?
A) Project Greenlight
B) Project Runway
C) Project X
D) Project Ilevomit
Correct Answer:

Verified
Correct Answer:
Verified