Multiple Choice
Realignment describes:
A) The change in a project portfolio with an addition of a new project.
B) The shifting of project resources from one to another.
C) The change in strategy for a firm.
D) The annual recasting of all project managers.
Correct Answer:

Verified
Correct Answer:
Verified