Your project team members do not have adequate training to complete project work and there are far fewer team members that what you need to complete your project activities according to your originally projected schedule.This situation represents an example of:


A) Execution risk.
B) Technical risk.
C) Commercial risk.
D) Legal risk.

Correct Answer: