Multiple Choice
The overall consequence of failure was 0.4 and curiously enough,the consequence of performance is twice that of reliability;the consequence of reliability is twice that of schedule;and the consequence of schedule is twice that of cost.What is the consequence of failure cost?
A) 0.091
B) 0.107
C) 0.123
D) 0.136
Correct Answer:

Verified
Correct Answer:
Verified
Q53: Sketch the risk level and opportunity curves
Q54: With a maturity risk of 0.3,a complexity
Q55: Your project team members do not have
Q56: The PostHoc Company specializes in justifying decisions
Q57: The residents of Enumclaw,Washington,live in the shadow
Q59: The mouse executive board meeting was drawing
Q60: Pick any three steps in the PRAM
Q61: The act of pairing a junior project
Q62: One phase of the project risk analysis
Q63: The Farm Fresh Egg project was too