Multiple Choice
Responding to an unforeseen threat that you either did not have a planned response for or has not been dealt with effectively by implementing your planned response is best described as a(n)
A) Mitigation plan.
B) Contingency.
C) Workaround.
D) Transference.
Correct Answer:

Verified
Correct Answer:
Verified