Multiple Choice
The firm set aside a little extra money just in case an unforeseen element of cost pushed the project beyond what they had budgeted.This extra money is called:
A) A rainy day fund.
B) A contingency reserve.
C) An escalation clause.
D) A sinking fund.
Correct Answer:

Verified
Correct Answer:
Verified
Q33: Responding to an unforeseen threat that you
Q34: The greatest project opportunity occurs when:<br>A)The project
Q35: A serious risk factor probably has:<br>A)A high
Q36: This scenario best describes a workaround:<br>A)Responding to
Q37: The first phase of a comprehensive project
Q39: The overall project risk factor is
Q40: The European Association for Project Management has
Q41: The exposure a firm opens itself to
Q42: What are the basic qualitative methods for
Q43: How do mentoring and cross-training mitigate risk?