Multiple Choice
The first phase of a comprehensive project risk assessment should be:
A) To assess the specific sources of risk at the outset of the project,including the need to fashion appropriate responses.
B) To make sure the project is well defined,including all deliverables,statement of work,and project scope.
C) To develop reasonable estimates of the impacts on the project of both the identified risks and the proposed solutions.
D) To produce a project risk management plan that proactively offers risk mitigation strategies for the project as needed.
Correct Answer:

Verified
Correct Answer:
Verified
Q32: The terpsichorean was familiar with the risks
Q33: Responding to an unforeseen threat that you
Q34: The greatest project opportunity occurs when:<br>A)The project
Q35: A serious risk factor probably has:<br>A)A high
Q36: This scenario best describes a workaround:<br>A)Responding to
Q38: The firm set aside a little extra
Q39: The overall project risk factor is
Q40: The European Association for Project Management has
Q41: The exposure a firm opens itself to
Q42: What are the basic qualitative methods for