Solved

A Project That Consists of Six Consecutive Tasks That Have

Question 46

Essay

A project that consists of six consecutive tasks that have average duration and worst-case duration estimates (in days)as shown in the table.Use Newbold's method to determine the aggregated two sigma buffer for this project.How does the project buffer computed this way compare with the estimation for project buffer offered by Goldratt?
 Activity  Average  Worst-Case  A 1421B2028C1623D815E919\begin{array} { | l | l | l |} \hline\text { Activity } & \text { Average } & \text { Worst-Case } \\\hline \text { A } & 14 & 21 \\\hline B & 20 & 28 \\\hline\mathrm {C } & 16 & 23 \\\hline \mathrm { D } & 8 & 15 \\ \hline E & 9 & 19 \\\hline \end{array}

Correct Answer:

verifed

Verified

The Newbold estimate is calculated as:
?...

View Answer

Unlock this answer now
Get Access to more Verified Answers free of charge

Related Questions