Multiple Choice
ABC project organization has one workstation that is capable of generating the drawings that their clients study before accepting ABC's bid.ABC is currently in the midst of three proposal projects and knows which proposed project will be most profitable and which will be least profitable.The workstation is scheduled so that the most profitable project's work is done first and the least profitable project work is done last.This is an example of:
A) Identifying a constraint.
B) Exploiting a constraint.
C) Elevating a constraint.
D) Subordinating a system.
Correct Answer:

Verified
Correct Answer:
Verified
Q95: What is the difference between the critical
Q96: What is Agile PM and what makes
Q97: A product backlog is the final list
Q98: A project consists of six consecutive
Q99: Extreme programming advocates a large development staff,several
Q100: CCPM advocates performing all non-critical activities:<br>A)As late
Q101: A scrum is one iteration of the
Q102: Successful implementation of CCPM depends on first:<br>A)Identifying
Q104: What are some arguments against the XP
Q105: Your boss catches you at the water