Multiple Choice
Successful implementation of CCPM depends on first:
A) Identifying the critical chain that meanders through the project organization's portfolio of projects.
B) Identifying the constraint that holds hostage the project organization's other resources.
C) Examining and changing the culture of the project organization.
D) Exploiting the drum by using it to subordinate the existing PERT network.
Correct Answer:

Verified
Correct Answer:
Verified