Solved

A Project Consists of Six Consecutive Tasks That Have Average

Question 98

Multiple Choice

A project consists of six consecutive tasks that have average duration and worst-case duration estimates (in weeks) as shown in the table.Use Newbold's method to determine the aggregated two sigma buffer for this project.  Activity  Average  Worst-Case A1014B24C612D813.5E912F575\begin{array} { | l | l | l | } \hline \text { Activity } & \text { Average } & \text { Worst-Case } \\\hline \mathrm { A } & 10 & 14 \\\hline \mathrm { B }& 2 & 4 \\\hline \mathrm { C } & 6 & 12 \\\hline \mathrm { D } & 8 & 13.5 \\\hline \mathrm { E } & 9 & 12 \\\hline \mathrm { F } & 5 & 75 \\\hline\end{array}


A) 5 days
B) 6 days
C) 7 days
D) 9 days

Correct Answer:

verifed

Verified

Unlock this answer now
Get Access to more Verified Answers free of charge

Related Questions