The Minimum Late Finish Time rule stipulates that:
A) The earliest late finishers are scheduled last.
B) The latest early finishers are scheduled first.
C) The earliest late finishers are scheduled first.
D) The latest late finishers are scheduled first.
Correct Answer:

Verified
Correct Answer:
Verified