Multiple Choice
What information is usually provided on a resource-usage calendar?
A) The tasks,the precedence requirements,and the money per unit time needed to reduce them.
B) The personnel,their hourly wage or salary,and the number of hours per week they are available.
C) The personnel,their responsibility for certain tasks,and the number of hours per week they are available.
D) The tasks,the people and equipment available,and the ownership and reporting relationships among them.
Correct Answer:

Verified
Correct Answer:
Verified
Q30: Consider the portfolio of projects described
Q31: A project consisting of six activities
Q32: Use the project described in the
Q33: Consider the project that is neatly
Q34: The project described in the table
Q36: A project consists of eleven activities
Q37: A project consists of eleven activities
Q38: <img src="https://d2lvgg3v3hfg70.cloudfront.net/TB6815/.jpg" alt=" -The project represented
Q39: The Minimum Late Finish Time rule stipulates
Q40: <img src="https://d2lvgg3v3hfg70.cloudfront.net/TB6815/.jpg" alt=" -Resource loading charts