Solved

A Project Consists of Eleven Activities (All Times Are Given

Question 37

Multiple Choice

A project consists of eleven activities (all times are given in days) and has worker requirements as indicated in the table.Assume that all six workers employed by this organization are generalists and are able to work on any of the tasks.What is the fastest the project can be completed?  Activity  Activity time  Workers Needed  Predecessor  A 101 B 42 C 73 A D41 A  E 82 B F 93 C,E  G 131D H 142 E, G  J 133 FK101H,JL52 K\begin{array}{|l|l|l|l|}\hline \text { Activity } & \text { Activity time } & \text { Workers Needed } & \text { Predecessor } \\\hline \text { A } & 10 & 1 & \\\hline \text { B } & 4 & 2 & \\\hline \text { C } & 7 & 3 & \text { A } \\\hline \mathrm{D} & 4 & 1 & \text { A } \\\hline \text { E } & 8 & 2 & \mathrm{~B} \\\hline \text { F } & 9 & 3 & \text { C,E } \\\hline \text { G } & 13 & 1 & \mathrm{D} \\\hline \text { H } & 14 & 2 & \text { E, G } \\\hline \text { J } & 13 & 3 & \mathrm{~F} \\\hline \mathrm{K} & 10 & 1 & \mathrm{H}, \mathrm{J} \\\hline \mathrm{L} & 5 & 2 & \mathrm{~K} \\\hline\end{array}


A) 54 days
B) 56 days
C) 58 days
D) 60 days

Correct Answer:

verifed

Verified

Unlock this answer now
Get Access to more Verified Answers free of charge

Related Questions