If an Activity's Progress Is Defined as 0% Until the Activity

Question 25

Multiple Choice

If an activity's progress is defined as 0% until the activity is complete,the project manager is using:


A) The 50/50 rule.
B) The all or nothing rule.
C) The 0/100 rule.
D) The Do Not Pass Go rule.

Correct Answer: