Use the Earned Value Table for Project Makeready to Calculate
Question 22
Question 22
Multiple Choice
Use the earned value table for Project Makeready to calculate the estimated cost to completion. Activity Irstall fixtures Refinish floors Replace doors Complete tiling Irstall back door Landscaping Monthly Plarn Monthly Act 7325325550142505508005502185350435550282751,2001,4751,100355658751,4401,65042225200425550493503501,100 plan 5756356251,7651,1005505,2508 Complete 100%100%100%80%70%25%
A) $4,285 B) $5,250 C) $6,050 D) $7,645