Use the Earned Value Table for Project Makeready to Determine

Question 1

Multiple Choice

Use the earned value table for Project Makeready to determine the earned value at week 49.  Activity 7142128354249 Plan %/1 Complete  Install fixtures 325250575100% Refinish floors 55085635100% Replace doors 350275625100% Complete tiling 1,2005651,76580% Install back door 8752251,10070% Landscaping 20035055025% Monthly Plan 3258004351,4751,4404253505,250 Monthly Act 5505505501,1001,6505501,100\begin{array} { | l | l | l | l | l | l | l | l | l | l | } \hline \text { Activity } & 7 & 14 & 21 & 28 & 35 & 42 & 49 & \text { Plan } & \% / 1 \text { Complete } \\\hline \text { Install fixtures } & 325 & 250 & & & & & & 575 & 100 \% \\\hline \text { Refinish floors } & & 550 & 85 & & & & & 635 & 100 \% \\\hline \text { Replace doors } & & & 350 & 275 & & & & 625 & 100 \% \\\hline \text { Complete tiling } & & & & 1,200 & 565 & & & 1,765 & 80 \% \\\hline \text { Install back door } & & & & & 875 & 225 & & 1,100&70 \% \\\hline \text { Landscaping } & & & & & & 200 & 350 & 550 & 25 \% \\\hline \text { Monthly Plan } & 325 & 800 & 435 & 1,475 & 1,440 &425 & 350 & 5,250 & \\\hline \text { Monthly Act } & 550 & 550 & 550 & 1,100 & 1,650 & 550 & 1,100 & & \\\hline\end{array}


A) $4,950
B) $6,050
C) $4,155
D) $5,250

Correct Answer:

verifed

Verified

Related Questions