Multiple Choice
The cycle time (CT) necessary in a product layout is determined by:
A) number of workstations/sum of task times.
B) operating time per day/desired output per day.
C) number of workstations multiplied by the sum of task times.
D) operating time per day multiplied by desired output per day.
E) sum of task times/number of workstations.
Correct Answer:

Verified
Correct Answer:
Verified
Q15: An advantage of a U-shaped production line
Q19: Using the method developed by Richard Muther,which
Q20: The maker of the world-famous Widget needs
Q21: A company is designing a product layout
Q22: A consultant needs to locate four departments-waiting
Q23: QRS Corp.is designing a product layout for
Q26: A job shop processing system tends to
Q27: Product layouts achieve high utilization of labour
Q28: In cellular layouts,machines and equipment are grouped
Q29: A possible disadvantage of a product layout