A Hierarchical Listing of What Must Be Done During the Project

Question 13

Multiple Choice

A hierarchical listing of what must be done during the project is called:


A) work breakdown structure (WBS) .
B) program evaluation and review technique (PERT) .
C) planning matrix.
D) crashing.
E) critical path method (CPM) .