Multiple Choice
Which action can managers take if capacity requirements planning (CRP) indicate one or more work stations are projected to be under loaded or over loaded?
A) Shifting some orders to adjacent periods.
B) Transferring employees from other areas.
C) Scheduling overtime.
D) Revise the MPS and MRP.
E) All of the choices are options.
Correct Answer:

Verified
Correct Answer:
Verified