Essay
Develop a material requirements plan for end item P and its components, given the tree below. Assume that all lead times are one week, and that lot-for-lot ordering is used except for item F, which is ordered in multiples of 400 units.
One hundred units of P are needed at the start of each of weeks 4 and 8.
Beginning inventories are: 20 P, 100 A, and 200 F.
Scheduled receipts are: 800 F at the start of week 1.