Multiple Choice
According to the NPV rule,all projects should be accepted if NPV is positive when discounted at the:
A) internal rate of return.
B) opportunity cost of capital.
C) risk-free interest rate.
D) accounting rate of return.
Correct Answer:

Verified
Correct Answer:
Verified
Related Questions
Q65: For most managers,discounted cash-flow analysis is in
Q66: As long as the NPV of a
Q67: The profitability index selects projects based on
Q68: Occasionally projects may have positive initial cash
Q69: The modified internal rate of return can
Q71: A currently used machine costs $10,000 annually
Q72: What is the NPV for the following
Q73: What is the IRR of a project
Q74: A project with an IRR that is
Q75: If a project has a cost of