Multiple Choice
Which of the following is not usually necessary in order to have an effective MRP system?
A) a computer and software
B) an accurate bill of materials
C) lot-for-lot ordering
D) an up-to-date master schedule
E) integrity of file data
Correct Answer:

Verified
Correct Answer:
Verified