menu-iconExamlexExamLexServices

Discover

Ask a Question
  1. All Topics
  2. Topic
    Business
  3. Study Set
    Project Management
  4. Exam
    Exam 6: Developing a Project Plan
  5. Question
    ________ Activities Are to Be Completed Immediately Following a Particular
Solved

________ Activities Are to Be Completed Immediately Following a Particular

Question 94

Question 94

Multiple Choice

________ activities are to be completed immediately following a particular activity.


A) Merge
B) Burst
C) Predecessor
D) Successor
E) Critical

Correct Answer:

verifed

Verified

Unlock this answer now
Get Access to more Verified Answers free of charge

Related Questions

Q1: When translated into a project network, a

Q23: In the network computation process what is

Q34: The WBS identifies dependencies, the sequencing of

Q85: The backward pass in project network calculations

Q86: What is a lag and why would

Q87: A(n) _ is an element in the

Q88: It is possible to have more than

Q89: If testing cannot be completed any earlier

Q90: In developing a project network, each activity

Q93: In an AOA network an activity is

Examlex

ExamLex

About UsContact UsPerks CenterHomeschoolingTest Prep

Work With Us

Campus RepresentativeInfluencers

Links

FaqPricingChrome Extension

Download The App

Get App StoreGet Google Play

Policies

Privacy PolicyTerms of ServiceHonor CodeCommunity Guidelines

Scan To Download

qr-code

Copyright © (2025) ExamLex LLC.

Privacy PolicyTerms Of ServiceHonor CodeCommunity Guidelines