Multiple Choice
Which of the following is a good condition for bottom-up estimating?
A) Strategic decision making
B) Internal, small project
C) Fixed price contract
D) High uncertainty
E) Both C and D are good conditions for bottom-up estimating
Correct Answer:

Verified
Correct Answer:
Verified
Related Questions
Q2: A good starting point for developing time
Q11: If time and costs are important to
Q20: Estimates that are usually derived from analogy
Q22: The _ method for estimating project time
Q26: Typical kinds of costs found in a
Q28: The use of past experience is almost
Q29: Phase estimating uses both the bottom-up and
Q66: Jose is forecasting project time and cost
Q71: The salary of the project manager and
Q95: Identify the three major categories of project