    Exam 5: Estimating Project Times and Costs
  5. Question
    ______ Estimates Are Most Likely to Use Low Cost, Efficient
Solved

______ Estimates Are Most Likely to Use Low Cost, Efficient

Question 66

Question 66

Multiple Choice

______ estimates are most likely to use low cost, efficient methods.


A) Apportion
B) Ratio
C) Top-down
D) Bottom-up
E) All of these are equally likely

Correct Answer:

verifed

Verified

Unlock this answer now
Get Access to more Verified Answers free of charge

Related Questions

Q38: If a project is internal to the

Q62: The prevailing belief in some firms that

Q63: People working on prototype development needing time

Q64: Which of the following is not one

Q65: The accuracy of top-down estimates will typically

Q67: In the _ method of top-down estimating,

Q68: The estimating factor known as _ considers

Q69: Design flaws being revealed after the fact,

Q70: A typical statement in actual practice is

Q89: The bottom-up approach for estimating times and

Examlex

ExamLex

About UsContact UsPerks CenterHomeschoolingTest Prep

Work With Us

Campus RepresentativeInfluencers

Links

FaqPricingChrome Extension

Download The App

Get App StoreGet Google Play

Policies

Privacy PolicyTerms of ServiceHonor CodeCommunity Guidelines

Scan To Download

qr-code

Copyright © (2025) ExamLex LLC.

Privacy PolicyTerms Of ServiceHonor CodeCommunity Guidelines