Short Answer
The prevailing belief in some firms that detailed estimating takes too much time and is not worth the effort or that it is impossible to predict the future is an example of the ________ factor.
Correct Answer:

Verified
organization culture
Explanation: Organi...View Answer
Unlock this answer now
Get Access to more Verified Answers free of charge
Correct Answer:
Verified
Explanation: Organi...
View Answer
Unlock this answer now
Get Access to more Verified Answers free of charge
Q38: If a project is internal to the
Q57: The function point method of time and
Q58: At the strategic level top-down estimating methods
Q60: Using the _ method of forecasting project