Multiple Choice
People working on prototype development needing time to interact with the design engineers after the design is completed is an example of:
A) Hidden interaction costs
B) Things going wrong on a project
C) Normal conditions not applying
D) Changes in project scope
E) None of these are correct
Correct Answer:

Verified
Correct Answer:
Verified