Question 37

Multiple Choice

What should the project manager do if it is determined that the net present value is negative but the internal rate of return is less than the required rate of return?


A) Decrease the required rate of return.
B) Reject the project.
C) Increase the required rate of return.
D) Calculate the profitability index.