In a Project Cost-Duration Graph, total project costs are a sum of
A) Labor, material and equipment costs.
B) Direct costs plus interest.
C) Direct labor costs and the project manager's salary.
D) Direct costs and the project manager's salary.
E) Direct and indirect costs.