Multiple Choice
Regina's boss has told her that her project is very important.If the critical path is delayed, she will be given whatever she needs to get it back on schedule.Her project is classified as ________ constrained.
A) Time
B) Quality
C) Cost
D) Performance
E) Resource
Correct Answer:

Verified
Correct Answer:
Verified