Which of the Following Top-Down Methods Is Used When Projects

Question 37

Multiple Choice

Which of the following top-down methods is used when projects closely follow past projects in regard to features and costs of those features, and result in costs being assigned by percentages to major segments of the project?


A) Apportion
B) Function point
C) Phase estimating
D) Learning curve
E) Consensus

Correct Answer: