Multiple Choice
The approved set of procedures that describe how modifications to the project deliverables and documentation will be managed and controlled are collectively known by which of the following terms?
A) scope statement
B) change control system
C) configuration management plan
D) scope management plan
Correct Answer:

Verified
Correct Answer:
Verified