Multiple Choice
Which of the following statements is true concerning the adoption of rolling wave planning in project management?
A) It is facilitated when the second level of the work breakdown structure is organized by phase or design components.
B) It is initially cumbersome,often delaying a prompt and timely project start.
C) It often creates a situation known as "analysis paralysis."
D) It requires detailed bottom-up estimating for every WBS component
Correct Answer:

Verified
Correct Answer:
Verified