Multiple Choice
All of the following elements should be included in a project scope statement EXCEPT:
A) project boundaries or exclusions
B) names of the project team members
C) assumptions and constraints that may limit or influence project work
D) key deliverables with acceptance criteria
Correct Answer:

Verified
Correct Answer:
Verified