Multiple Choice
Creating a realistic schedule is often an iterative process because several factors can limit how fast a project can be completed.All of the following factors can limit how fast a project can be scheduled and completed EXCEPT:
A) logical order
B) imposed dates
C) resource availability
D) quality metrics