    An Activity That Logically Comes Before a Dependent Activity in a Schedule
Solved

An Activity That Logically Comes Before a Dependent Activity in a Schedule

Question 33

Question 33

Multiple Choice

An activity that logically comes before a dependent activity in a schedule is called a ___:


A) leader activity
B) predecessor activity
C) successor activity
D) mandatory activity

Correct Answer:

verifed

Verified

Unlock this answer now
Get Access to more Verified Answers free of charge

Related Questions

Q13: <img src="https://d2lvgg3v3hfg70.cloudfront.net/TB6636/.jpg" alt=" Figure 7-5 Duration

Q29: Creating a realistic schedule is often an

Q30: Except in rare circumstances,project teams should not

Q31: The amount of time a schedule activity

Q32: Milestones are important points in a project

Q35: A mandatory dependency in a relationship that

Q36: Describe "slack" and how you can use

Q37: If a project manager delays the start

Q48: The length of time to perform an

Q53: Which of the following responses identifies a

Examlex

ExamLex

About UsContact UsPerks CenterHomeschoolingTest Prep

Work With Us

Campus RepresentativeInfluencers

Links

FaqPricingChrome Extension

Download The App

Get App StoreGet Google Play

Policies

Privacy PolicyTerms of ServiceHonor CodeCommunity Guidelines

Scan To Download

qr-code

Copyright © (2025) ExamLex LLC.

Privacy PolicyTerms Of ServiceHonor CodeCommunity Guidelines