Scrum does not use any of the conventional project management tools like Gantt charts or network diagrams.

Correct Answer:

verifed

Verified

Unlock this answer now
Get Access to more Verified Answers free of charge

Related Questions

Q43: _is the Agile principle where the project

Q44: Scrum relies on three key roles. A

Q45: The more the project scope is unknown,

Q46: _is the Agile principle that describes the

Q47: Continuous improvement is a principle found in

Q49: When faced with a project having multiple

Q50: Scrum uses a series of coordinated meetings

Q51: _project management requires a fairly high degree

Q52: The goal of each sprint is to

Q53: Which of the following is not a

Examlex

ExamLex

About UsContact UsPerks CenterHomeschoolingTest Prep

Work With Us

Campus RepresentativeInfluencers

Links

FaqPricingChrome Extension

Download The App

Get App StoreGet Google Play

Policies

Privacy PolicyTerms of ServiceHonor CodeCommunity Guidelines

Scan To Download

qr-code

Copyright © (2025) ExamLex LLC.

Privacy PolicyTerms Of ServiceHonor CodeCommunity Guidelines