Which of the following correctly calculates an activity's cost slope?
A) (normal cost - crash cost) / (normal time - crash time)
B) (crash cost - normal cost) / (normal time - crash time)
C) (normal time - crash time) / (crash cost - normal cost)
D) (normal time - crash time) / (normal cost - crash cost)