Multiple Choice
The critical path in a project network is the
A) Shortest path through the network.
B) Longest path through the network.
C) Network path with the most difficult activities.
D) Network path using the most resources.
E) Network path with the most merge activities.
Correct Answer:

Verified
Correct Answer:
Verified
Related Questions
Q1: When translated into a project network, a
Q4: How does the WBS differ from the
Q5: A _ activity is one that has
Q6: An activity that has more than one
Q7: A(n)_ activity has more than one dependency
Q8: What is the Concurrent Engineering Approach and
Q11: The amount of delay within a task
Q50: If a network has more than one
Q66: The backward pass through a project network
Q76: Burst activities have more than one activity