Multiple Choice
A _________ activity is one that has more than one activity taking place at the same time.
A) Burst
B) Merge
C) Parallel
D) None of these choices are correct.
Correct Answer:

Verified
Correct Answer:
Verified
Related Questions
Q1: When translated into a project network, a
Q3: The critical path in a project network
Q4: How does the WBS differ from the
Q6: An activity that has more than one
Q7: A(n)_ activity has more than one dependency
Q8: What is the Concurrent Engineering Approach and
Q11: The amount of delay within a task
Q50: If a network has more than one
Q66: The backward pass through a project network
Q76: Burst activities have more than one activity